Building Control

Following on from the Priory Hall and Pyrites Debacles it stood to reason that the building industry would be more stringently controlled. DTW welcome the new regulations although onerous and time consuming they will highlight the non compliant builders and lead to better construction practice and standards. DTW are members of the Construction Industry Federation [ CIF] and CIRI approved.
DTW are very happy to comply with the new regulations as they that they will give more comfort and certainty to the Owner/Developer.
A new regime for certification under the Building Control (Amendment) Regulations 2013

On March 8th 2013, Phil Hogan, Minister for the Environment, Community and Local Government signed the Building Control (Amendment) Regulations 2013 (the “Regulations”) into law, which will be effective from 1 March 2014. The enactment of the Regulations followed a wide-ranging and often heated public consultation process which had begun in April 2012 with the publication of draft regulations.

Brief Overview of the Regulations

1 Focus of the Regulations

The Regulations introduced a substantial number of changes to the current system of certification of compliance with Building Regulations. Most significant is the revision of the commencement notice together with the introduction of three new types of mandatory certificates, in prescribed form; (i) The Certificate of Compliance (Design) (the “Design Certificate”) (ii) Certificate of Compliance (Undertaking by Assigned Certifier) / Certificate of Compliance (Undertaking by Builder) (together, the “Undertakings”) and (iii) Certificate of Compliance on Completion (the “Completion Certification”).

The Regulations require a continued focus on compliance with Building Regulations, from design stage to completion. Prior to the works commencing, the design of the works must be certified as complying with Building Regulations by the execution of the Design Certificate. The building owner will also nominate at commencement stage (through notices in prescribed form) an “Assigned Certifier” and a “Builder”. The “Assigned Certifier” and “Builder” will be tasked with confirming that the completed works comply with Building Regulations by executing the Completion Certificate and must also formally undertake to carry out this task at commencement stage.

The Regulations are intended to work in tandem with a “Code of Practice for Inspection and Certification” which will inform the “Assigned Certifier” and “Builder” how to manage their respective roles including the preparation of an inspection plan. The Regulations specifically state that where works are “inspected and certified in accordance with the guidance contained in the Code of Practice…this shall, prima facie, indicate compliance with the relevant requirements of these regulations”. The Code, however, has not yet been made publicly available, even in draft form. A recent indication from the Department is that the Code will be published by the end of April 2013.

Building-Regulations-from-2

2 The Commencement Notice

While the requirement to submit a Commencement Notice is not new, the regulations have significantly altered the scope and effect of this notice. Article 9 now requires that a Commencement Notice in prescribed form be submitted with the following documentation:

(a) such plans, calculations, specifications and particulars as are necessary to demonstrate how the proposed works or building will comply with the requirements of the Second Schedule of the Building Regulations

(b) the Design Certificate

(c) the Notice of Assignment of Person to Inspect and Certify Works (Assigned Certifier) and Notice of Assignment of Builder

(d) The Undertakings (both of the Assigned Certifier and Builder)

3 The Design Certificate

This Certificate, to be completed by the building designer (a registered architect, builder surveyor or chartered engineer) must be submitted with the Commencement Notice, and requires confirmation that the plans etc., included with the notice have been prepared to demonstrate compliance with the applicable requirements of the Building Regulations and “have been prepared exercising reasonable skill, care and diligence by me, and prepared by other members of the owner’s design team and specialist designers whose design activities I have coordinated”.

4 Inspection and Certification of the Works – Assigned Certifier and Builder

The Assigned Certifier must also be a registered architect, building surveyor or chartered engineer and will be required to provide an undertaking, submitted with the Commencement Notice, to inter alia, “use reasonable skill, care and diligence, to inspect the works and to coordinate the inspection works of others and to certify following the implementation of the inspection plan by myself and others, for compliance with the requirements of the Second Schedule to the Building Regulations”.

The same person must also execute Part B of the Completion Certificate certifying that “the inspection plan drawn up in accordance with the Code of Practice…has been fulfilled by the under-signed and other individuals nominated therein having exercised reasonable skill, care and diligence and that the building or works is in compliance with the requirements of the Second Schedule of the Building Regulations…”

The Builder is also be required to provide an undertaking, submitted with the Commencement Notice identifying the works which he has been commissioned to undertake and confirming his own competence and those employed and engaged by him, to undertake such works. Further the Builder must also undertake the construct the works in accordance with the plans etc., submitted (or subsequently submitted) and to cooperate with the inspections set out in the inspection plan prepared by the Assigned Certifier. The Builder must also execute Part A of the Completion Certificate certifying that the works as completed have been constructed in accordance with plans and reliant on this, the works are in compliance with Building Regulations. Both the undertaking and the Completion Certificate are specifically required to be signed by a “Principal or Director of a building company only”.

5 Completion

A Completion Certificate, executed by both the Assigned Certifier and the Builder, must be submitted to Building Control Authority. The Completion Certificate must be accompanied by (i) such plans etc., as are required to outline how the completed works differ from the plans submitted at commencement, (ii) such plans as are required to outline how the completed works comply with the Building Regulations and (iii) the Inspection Plan implemented by the Assigned Certifier.

Works or buildings cannot be “opened, occupied or used” until the relevant particulars of the Certificate of Compliance on Completion are entered on a statutory register to be kept by the building control authority, however, the Regulations provide that the Completion Certificate may refer to “works, buildings, including areas within a building, or developments, including phases thereof…”, indicating that works can be completed in stages if necessary.

Conclusion